SITE-BUILT RECOVERY PLANTS

Since 1972, KCA has provided lab testing, engineering and/or field services for over 1,000 different gold recovery projects. KCA’s plants have earned an outstanding reputation for quality, simplicity, ease of start up and fail-safe operation. KCA can provide a complete turnkey project to process your ore in the most cost effective manner.  KCA can handle your project from laboratory testing through gold production. KCA works throughout the world from our offices in Nevada, Mexico, and Australia.

KCA has provided on-site plants on a turn-key basis (design, engineering, startup) for operations such as La India, Mexico (17,250 tons per day) and San Martin, Honduras (20,000 tonnes per day).

KCA also provides design engineering, and construction/startup supervision for plants and complete mine/process installations. Examples are the 1500 tonne/day CIP (agitated leach) gold plant at Puquio Norte, Bolivia and the 20,000 tonne/day heap leach plant at Tarkwa, Ghana.

A list of projects for which KCA has fabricated on-site recovery plants is presented below.

Major on-site EPCM projects can found on our home page under Major Projects.

Precious Metal Plants

OperationLocationTypeSize
Bolkaradag TurkeyMerrill-Crowe & Agitated Leach Plant 200 tons/day
Dolores MexicoComminution Circuit to Existing MC 5600 tons/day
El CastilloMexico Carbon Adsorption1400 m³/hr
Hog Ranch United States Carbon Adsorption & Strip 4000 tons/day
Hycroft United States 5 Ton Caustic Strip 5 tons/day
Hycroft United States Merrill-Crowe 4772 m³/hr
Itos Bolivia Agitated Leach 600 tons/Day
Ivrindi Turkey Carbon Adsorption 3200 m³/hr
La Colorada Mexico Carbon Adsorption 1300 m³/hr
La India Mexico Carbon Adsorption 1400 m³/hr
Los Filos Mexico Carbon Adsorption 3600 m³/hr
Los Filos Mexico Pumping Expansion 4500 m³/hr
Los Filos Mexico Carbon Adsorption Expansion 900 m³/hr
Mascota Mexico Carbon Adsorption 340 m³/hr
Nixon Fork United States 1.5 Ton Zadra Strip 1.5 tons/day
Ocampo Heap Leach Mexico Merrill-Crowe 800 m³/hr
Ocampo Mill Mexico Merrill-Crowe 233 m³/hr
Pinos Altos Mexico Merrill-Crowe 551 m³/hr
Potosi Bolivia Merrill-Crowe 150 m³/hr
Puquio Norte Bolivia Carbon Adsorption & Zadra Strip (1.5-Tonne) 370 m³/hr
Puquio Norte Bolivia Carbon Regeneration 75 kg/hr
San Martin Honduras Carbon Adsorption 900 m³/hr
Sao Francisco Brazil Carbon Adsorption 700 m³/hr
Soledad Heap Leach United States Merrill-Crowe 660 m³/hr
South Area United States Carbon Adsorption 3500 m³/hr
Tambor Guatemala Gold Flotation 200 tons/day
Tambomayo Peru Merrill-Crowe 1200 m³/hr
Tarkwa Ghana Carbon Adsorption/Strip w/ Hot Zn Precip 700 m³/hr
Tarkwa II Ghana Carbon Adsorption Tower 230 m³/hr

Operation

Bolkaradag

Mascota

The above photo shows the CIC and stripping plant for the Mascota project as fabricated by KCA.

Bolkardag

The above photo shows the Merrill-Crowe plant, Mercury Retort, and Smelting Furnace for the Bolkardag project as fabricated by KCA.

A more complete description of the project as well as the full extent of KCA’s involvement may be found here.

Hog Ranch

Hog Ranch Heap

KCA performed the project engineering and construction management for this 4000 ton per day open pit heap leach gold operation. KCA had turnkey responsibility for offices, power and utilities, and infrastructure as well as processing. The project was brought into production after only 16 weeks of construction, ahead of schedule and under budget at a capital cost of US $7.7 million. The project was sold, after 18 months of successful operation, for a value exceeding 10 times the original investment.

As part of the initial capital installations, Hog Ranch installed 1,000,000 sq ft (90,000 sq m) of PVC leach pad, sufficient for the first year of operation.

KCA supplied this agglomerating drum and conveyor transport/stacking system for the Hog Ranch project. The ore was crushed to 3 inches (75 mm). This is a relatively coarse size that would not normally require agglomeration, but the ore contained up to 40% fine clay which made the heaps impermeable without agglomeration.

Itos

Itos is a US $ 17 million, 600 tonne/day agitated leach plant which recovers precious metals and base metals from previously processed flotation tailings using a complex acid leach process.

Ity

The plant at Ity, Ivory Coast, is typical of KCA’s smaller modular plants. This photo shows the carbon column adsorption/desorption circuit. In these smaller plants, gold is adsorbed then desorbed from the carbon in the same columns using an alcohol strip. Carbon is replaced once per year.

The desorption circuit of the Ity plant consists of a tank, a heater and solution recirculation system, an electrolytic cell (located in the container) and a smelting furnace to produce dore bars on site (not shown). The above two photos were taken at the KCA Reno fabrication yard. Modular plants are fully wet-tested in Reno before being shipped to site. Total setup time at remote sites is usually less than six weeks.

The recovery plant can be seen in the center of this view on site at the Ity project in the Ivory Coast. KCA can provide complete design, construction management, and startup services for mineral processing operations.

Potosi

The COMCO SILVER operation at Potosi, Bolivia, is a 1000-TPD dry grind/heap leach project treating an oxidized silver ore. This heap leach project is unique in that the ore is fine crushed to 8 mesh and then reduced in size by dry grinding to 20 mesh prior to agglomeration for heap leaching. Crushing is done in a three-stage system with a jaw crusher, cone crushers, and a Barmac impactor in closed circuit with an 8 mesh screen. Ore is then screened at 20 mesh, and oversize is dry-ground in a ballmill. The combined product is then agglomerated with cement and conveyor-stacked on a heap leach. KCA provided the original design and construction supervision, and the engineering supervision for subsequent expansion from 500 to 1000 TPD.

Puquio Norte

The COMCO SILVER operation at Potosi, Bolivia, is a 1000-TPD dry grind/heap leach project treating an oxidized silver ore. This heap leach project is unique in that the ore is fine crushed to 8 mesh and then reduced in size by dry grinding to 20 mesh prior to agglomeration for heap leaching. Crushing is done in a three-stage system with a jaw crusher, cone crushers, and a Barmac impactor in closed circuit with an 8 mesh screen. Ore is then screened at 20 mesh, and oversize is dry-ground in a ballmill. The combined product is then agglomerated with cement and conveyor-stacked on a heap leach. KCA provided the original design and construction supervision, and the engineering supervision for subsequent expansion from 500 to 1000 TPD.

The photo shows the carbon stripping and regeneration module built for Puquio Norte by KCA. The plant was built in Reno, then dismantled and reassembled in Bolivia.

San Martin

The San Martin, Honduras, project of Glamis Gold Ltd. is a 15,000 tonne/day heap leach which started production in early 2001. Head grade is 0.9 grams/tonne and recovery is 73%.

KCA provided the recovery plant on a complete turnkey guaranteed basis.

KCA fabricated technical components in Reno, and subcontracted in Honduras for tanks and structures.

Some photos are shown below.

The San Martin plant contains two trains with five carbon columns each. Total combined flow is 900 cu m/hr of solution (4000 gpm). The parallel trains allow for variation in flow between the dry season and the rainy season.

Equipment provided by KCA includes a carbon stripping and regeneration plant, and a complete gold room. KCA also provided a separate water treatment plant. KCA’s turnkey contract was about $2 million of the total $27 million project capital cost.

The ore is soft and requires agglomeration, but clay content is low so cement consumption is only 2.5 kg/tonne. Rainfall on site is about one meter per year.

Tambor

The 200 tonne per day partially assembled flotation process plant for the Tambor Project in KCA’s Reno yard.  The float cells and rear deck are mounted on standard shipping skids, and the rest is easily reassembled.