TÜMAD Mining Inc. Ivrindi Gold Project Dates: 2017 - 2019 Location: Ivrindi, Turkey 21,100 TPD - ADR Plant

Ivrindi is a 7.7 million tonne/year heap leach operation with a 3200 m3/hr ADR plant. KCA provided metallurgical flow­sheet development, followed by the process sections of a bankable feasibility study. 

KCA, together with our Turkish affiliate DAMA Madencilik (Ankara), supplied detailed engineering, fabrication, installation and startup of the plant for the Ivrindi Project located in Turkey, near the town of Ivrindi in the Balikesir province.